Thunder Bay Pulp and Paper – Single Point Connection Commissioning

Location: Thunder Bay, Ontario

Customer: Thunder Bay Pulp and Paper

Project Summary

As part of a major electrical infrastructure upgrade, our team completed the testing and commissioning of new and modified high-voltage (HV) and medium-voltage (MV) electrical equipment, protection relays, control systems, and monitoring infrastructure across multiple substations and powerhouse locations.

 

  • Commissioning of 121 kV breakers, disconnects, CVTs, surge arresters, and neutral grounding resistors at multiple substations.
  • Complete commissioning of two (2) new 15 kV switchgear lineups 
  • Testing and commissioning of new and modified protection relays for feeders, buses, transformers, generators, and line protections.
  • Testing of new mirrored bit and IE61850 communications for facility intertrip and blocking signals 
  • Commissioning of new generator and breaker controls (Easygen and LS6s) 
  • Commissioning and functional testing of load shedding module and load shedding scheme  
  • Commissioning of DC battery systems and support equipment.
  • Functional testing of breaker failure, transfer trip, and blocking signals with Hydro One through the existing NDS570s
  • Coordination and support for points testing with the IESO
  • Commissioning  of turbine generator synchronization circuits 
  • Startup support during integration of the new system